HPE Aruba Central Initial Configuration

As a prerequisite for Central configuration, switches are installed physically and onboarded to Central after initial unboxing and inventory. Please follow the procedure in the Data Center deploy central two-tier switch prep section.

Initial Configuration

This section demonstrates initial configuration of Central UI groups and sites and the assignment of switches to both configurations.

Switches with a common set of configuration elements should be assigned to the same Central UI group. In a Two-Tier data center, one group is defined for core switches and a second group for access switches.

Refer to the procedure in the HPE Aruba Central initial configuration section.